T CH/Sarcee

TRANSCANADA HIGHWAY – SARCEE TRAIL INTERCHANGE NEARS COMPLETION

Construction is 70 per cent complete on TransCanada Highway (TCH) – Sarcee Trail Interchange and is expected to be finished by September 1, 2017.
 
Both new bridge structures are nearing completion with traffic running over the new west bridge and under the new east bridge. Currently, all traffic has been moved temporarily to the new by-pass ramps until the work on the roundabout and the pedestrian underpass is complete.
 
This current traffic pattern will remain largely unchanged until the project finishes in late August. At this time the roundabout and remaining ramps will be fully functioning and full access to all local communities will be restored.
 
There will be on-going short term lane closures to perform some work through the summer. Our construction teams monitor the area daily and work hard to minimize delays for Calgary commuters.
 
Our goal is to get the roadwork complete first. Some work off the roadways will continue through the fall such as landscaped area rehabilitation, stormwater facility construction and site clean up.
 
Calgary’s Bowfort Road Project
 
The City of Calgary anticipates the Trans Canada Highway – Bowfort Road interchange will also be complete later this summer. For information on The City of Calgary Bowfort Road construction project, please call 311 from within the City or 403.268.CITY.
 
UPDATED JUNE 2017

Improving traffic flow

Improvements proposed for the Trans Canada Highway and Sarcee Trail Interchange will facilitate access to Trinity Hills development and improve the functionality of the existing interchange.

Trinity to fund improvements at TransCanada Highway and Sarcee Trail interchange

Trinity Development Group is working with the City of Calgary to fund and construct improvements to the interchange at Sarcee Trail and TransCanada Highway.
 
A key goal of the project improvements is to improve flow through of traffic in the area, and ensure that the Trinity Hills project does not impact traffic volumes and commute times for commuters living in surrounding areas. The changes will also provide access to the Trinity Hills development.
 
These interchange improvements will also eliminate conflict points, increasing safety for all drivers.
 

Included in the scope of the project are construction of two roadway bridge structures, a pedestrian underpass, and retaining walls. At the same time we will include rehabilitation of existing bridges and related earthworks, roadworks and utility works.

Traffic improvements mean uninterrupted traffic flow for commuters

The improvements to the TransCanada Highway/Sarcee Trail interchange are strategically designed to separate the higher volume ‘regional’ traffic movements from the ‘local traffic’ requiring access to the new development and adjacent communities. This design will allow those using the interchange to drive directly through without being impeded or impacted by the local community traffic.
 
traffic_map

BOWDALE CRESCENT ACCESS

In response to discussions with the community of Wilson Gardens, regarding the current construction access onto Sarcee Trail – TCH, the project team has made the following improvements:

  • The currently designated community exit location was relocated to the final, ultimate location and allows residents to leave the community without conflicting with vehicles entering the community as of December 2, 2016. The community entrance location will remain in the same location.
  • A deceleration lane has been added to the current ‘U-turn’ on Sarcee to ensure normal flow of traffic is maintained while allowing vehicles to slowly leave the main roadway prior to accessing the turning area.
  • The exit to southbound Sarcee Trail will be closed through the duration of the construction until the roundabout is operational

 
Updated April 2017
 

MINIMIZING CONSTRUCTION IMPACTS

The majority of the interchange work will take place off the existing roadways. This strategy will minimize the need for any full road closures or major detours. We anticipate there may be a need for short duration lane closures and speed reductions as we complete ramp connections and other features throughout the project.
 
Our goal is to minimize traffic impacts as much as possible.
 
The TCH-Sarcee Interchange is a joint project between The City of Calgary and Trinity. For continued updates on the project, please sign up for the newsletter below.
 

INFORMATION SESSION MATERIALS:

Learn more about the planned changes. Download the information session materials here.
 
Download the TransCanada – Sarcee Interchange Handout here
 

STAY TUNED to this page for updates on construction progress and traffic interruptions, and sign up for the Trinity Hills newsletter.
 

EMAIL
hello@trinityhills.ca
FACEBOOK
Like Us
TWITTER
Follow Us
MEDIA INQUIRIES
Email our media contact
Trinity Hills is a property of Trinity Development Group. For more information, please visit www.trinity-group.com.